òòò½ÊÓƵ

London Road improvements

Information about the project

We are improving the junctions and resurfacing London Road, between Easter Road and Meadowbank Terrace.

This will also include

  • upgrades to several of the signalised junctions and pedestrian crossing points
  • resurface sections of the pavement
  • renew traffic signals and streetlights
  • upgrade the surface water drainage facilities.

We have scheduled this work to start on Monday 10 July 2023.

It will take approximately 26 weeks to complete and be carried out in six phases which are outlined below. 

Junction upgrades

Phase 1 Junction of London Road with Montrose Terrace

Phase 2 Junction of London Road with Abbey Lane

Phase 3 Junction of London Road with Marionville Road

Phase 4 Junction of London Road with Cambusnethan Street

Phase 5 Junction of London Road with Wishaw Terrace

Road Resurfacing

Phase 6  London Road